Maida Vale Tube: Update


As promised, the latest update from TfL on "progress" to finishing Maida Vale tube:
  • Tiling and stair-nosing of the fixed staircase completed;
  • Installation of external roof lighting;
  • Installation of the fan control unit in the communications equipment room;
  • Ongoing mechanical installations in the station control point;
  • Completion of ventilation systems;
  • Tiling of wall and floor in circulation areas;
  • Waterproof render installed in the water meter room;
  • Circuit testing in the back of house rooms, and;
  • Painting of entrance and emergency stairs.

Despite this pretty list - which seems to indicate that the best part of a month's work consists of the occasional bit of tiling, grouting and painting - we remain unconvinced that TfL really have their foot on the gas on this. Indeed, only a couple of weeks ago we heard that a TfL source had suggested that the July completion target is wholly unrealistic - and December is a much more likely date.

As a result, we have asked for a list of remaining items to be completed, with target completion dates against each - so we can propelry measure progress and watch as TfL fall behind. We'll let you know whether TfL provide one.

Lee