Maida Vale Tube: Update
- Tiling and stair-nosing of the fixed staircase completed;
- Installation of external roof lighting;
- Installation of the fan control unit in the communications equipment room;
- Ongoing mechanical installations in the station control point;
- Completion of ventilation systems;
- Tiling of wall and floor in circulation areas;
- Waterproof render installed in the water meter room;
- Circuit testing in the back of house rooms, and;
- Painting of entrance and emergency stairs.
Despite this pretty list - which seems to indicate that the best part of a month's work consists of the occasional bit of tiling, grouting and painting - we remain unconvinced that TfL really have their foot on the gas on this. Indeed, only a couple of weeks ago we heard that a TfL source had suggested that the July completion target is wholly unrealistic - and December is a much more likely date.
As a result, we have asked for a list of remaining items to be completed, with target completion dates against each - so we can propelry measure progress and watch as TfL fall behind. We'll let you know whether TfL provide one.
Lee
Labels: Tube